October 2018

  • Deconstruction of the Community School is at approximately 75% completion.
  • Haul away of deconstruction materials is ongoing, and at about 25% completion.
  • OPA portables are occupied.
  • Plans are underway with kitchen management for the new central kitchen startup.
  • Kitchen Equipment is on order and delivery scheduled.
  • Saw cutting of new kitchen floor for utilities, installation and concrete replacement complete.
  • Trusses for new kitchen expected to arrive mid-November.
  • Framing for new kitchen under way.
  • Abatement of community school and new kitchen area complete, with the exception of close-out.  